Cone Zone 6/4: Repaving in Tucson and I-19 near Nogales

Posted: Jun 4, 2012 11:09 AM
Updated: Jun 5, 2012 9:20 AM


Bookmark and Share
Rating:

0.0 (0 votes)

NORTH CAMPBELL AVENUE REPAVING PROJECT AND BIKE LANE PROJECT

On Monday, June 4, 2012, between the hours of 5:00 a.m. and 6:00 p.m., the Pima County Department of Transportation along with its contractor, Southern Arizona Paving, will be performing a milling and asphalt paving treatment on Campbell Avenue from River Road to Skyline/Sunrise Drive.

This project will also reduce the four-lane section of North Campbell Avenue that begins south of Camino La Brinca and extends north to Avenida de Posada. The existing four-lane section on North Campbell Avenue will be reduced to a new two-lane section (one-lane in each direction) and bike lanes on each side to improve safety for roadway users. The new pavement will replace deteriorating pavement with a new asphalt surface and new striping for continuous bike lanes along this segment.

On Monday, June 4, 2012, the contractor will be starting preliminary work and begin the milling and paving on Thursday, June 7, 2012. Work is expected to be completed by the end of June 2012.

Traffic will be detoured onto a milled surface shoulder and flag personnel/pilot cars will direct traffic through the work zone area.

Please approach the area with caution and obey all traffic control devices.

OVERLAY PAVING PROJECT ON INA ROAD: WADE ROAD TO SILVERBELL ROAD AT MARANA TOWN LIMITS

On Tuesday, June 5, 2012, between the hours of 5:00 a.m. to 6:00 p.m., the Pima County Department of Transportation along with its contractor, Granite Construction, will be performing an overlay pavement treatment on Ina Road from Wade Road to Silverbell Road at Marana town limits.

On Tuesday, June 5, 2012, the contractor will be starting preliminary work and begin the overlay paving on Wednesday, June 6, 2012. Work is expected to be completed by the end of the week.

Traffic will be directed through the work zone area by flaggers, and Pima County Sheriff's deputies will be on-site.

Please approach the area with caution and obey all traffic control devices.

Pavement work on Interstate 19 frontage roads north of Nogales

The Arizona Department of Transportation has scheduled pavement maintenance on the southbound and northbound I-19 frontage roads just north of Nogales. There will be lane restrictions as crews apply a coat of rejuvenating oil to the roadway surface. The work is scheduled as follows:

Monday (June 4)
• The northbound I-19 frontage road from Rock Corral Road to Avenida Goya will have intermittent lane closures from 7 a.m. to 3 p.m.
• One lane will be open at all times.

Crews will be on site to direct traffic. Drivers should expect up to 15 minute delays.

Comments

KVOA.com is Social!

Most Popular

DON'T MISS THESE!

Thumbnail
FC TUCSON

Check out the latest events FC Tucson has scheduled.

Thumbnail
SEASON 4 HOPE

Help those in need this holiday season

Thumbnail
SUBMIT NEWS TIP

Click here to submit a news tip to us!

Thumbnail
NEWS 4 TUCSON ON FACEBOOK

Become a Facebook Fan!

Thumbnail
@KVOA ON TWITTER

Follow us!

Thumbnail
BECOME A MEMBER

Sign up on KVOA.com for newsletters, exclusive deals, and more!

Thumbnail
KVOA.COM LATEST CONTESTS

Win! Win! Win!

Thumbnail
KVOA MOBILE APPS

Get news, weather and more on your smartphone and tablet!

Thumbnail
TEXT ALERTS

Get texts for news, traffic, deals and more!

Thumbnail
KRISTI'S KIDS

Stories and videos with Kristi's Kids

Thumbnail
NEWS 4 TUCSON @ 4

What's happening on News 4 @ 4

Thumbnail
ADVERTISE WITH KVOA.COM

Let us help grow your business

Thumbnail
COMMUNITY CALENDAR

What's happening?

Thumbnail
KVOA PROGRAM SCHEDULE

What's on KVOA and when!

Thumbnail
CONTACT US

Contact info for our department heads

Thumbnail
FCC ONLINE PUBLIC FILE

FCC Public File of Records, Reports, and More

Thumbnail
MEET US!

KVOA's on air personalities!

Thumbnail
KVOA CAREERS

Work at News 4 Tucson

Thumbnail
RSS FEEDS

Complete feeds of all KVOA.com stories